DEP Issues Penalty, Allows Sunoco to Resume Construction

DEP entered into a Consent Order and Agreement with Sunoco that issued a $12.6 million penalty on Sunoco and lifted the order suspending construction.

On January 3, 2018, the PA Department of Environmental Protection issued an Administrative Order directing Sunoco to immediately suspend all work on the Mariner East 2 pipeline project authorized by DEP permits.  

On February 8, 2018, DEP and Sunoco entered into a Consent Order and Agreement.  From DEP’s news release:  “The Pennsylvania Department of Environmental Protection (DEP) announced that it has issued a $12.6 million civil penalty to Sunoco Pipeline, LLP for permit violations related to the construction of the Mariner East 2 pipeline project. DEP and Sunoco have entered into a Consent Order and Agreement memorializing the penalty. As a result of the strict Consent Order and Agreement, which includes a historic civil penalty and a stringent compliance review, DEP has lifted the order suspending DEP-permitted operations.”

DEP also posted a Summary of Actions and Outcomes required by their January 3rd Administrative Order.

Facebook Twitter Google Plus Email

Other News in WWT News Flash Items

Reporting Potholes

Posted on: February 15, 2018

New Arrivals

Posted on: February 15, 2018
CVT ExtensionStudyCoverThumb

Chester Valley Trail (CVT) Extension Study

Posted on: February 14, 2018
Landscapes 3

Chester County Long Term Plan

Posted on: February 12, 2018
Egg hunt

Egg Hunt March 24 at Boot Road Park

Posted on: February 12, 2018